Case Study Overview
Red7Marine provided the marine plant & specialist personnel to undertake the construction of the new oil jetty installed in advance of the main reclamation works for the London Gateway Port development.
At a glance
- Date: January 2009
- Programme Duration: 22 months
- Project Number: 2036
- Value: £3.86m
- Client: Laing O’Rourke
- Principal Contractor: Laing O’Rourke
The Solution
The works comprised driven steel raking & vertical steel piles to support mooring & berthing dolphins together with driven steel clutched tubular piles to form an underwater retaining wall to the rear of the new berth pocket.
Red7Marine designed & fabricated the temporary works piling gates & deployed crane barges, transport pontoons & jack up barges, together with the associated crew & supervision, in order to facilitate construction.
Following piling works the berthing & mooring dolphins were constructed from pre-cats & cast in-situ reinforced concrete & in turn these were then fitted with fender units & mooring equipment.