Earlier this year, Red7Marine successfully completed a £1.7M piling project at the Port of Dover, working alongside Principal Contractor, Knights Brown.

We’re excited to share the following video of operations in full swing, which involved the construction of a new outer wave wall using our 250t Haven Seariser 4 jack-up barge and Haven Seaforth flat top barge.

The project consisted of a detached, piled wave wall screen of approximately 70m in length made up of 59no. 1067mm diameter 27m long tubular piles at the entrance to the new marina within Dover Harbour. All piles were installed by the Red7Marine team.