Case Study Overview
The Westminster Pier Extension allows more frequent River Bus services between Woolwich and North Greenwich to Westminster. The extension is a key part of the River Action Plan to improve TfL’s piers and increase capacity for passengers before 2020.
At a glance
- Location: Westminster, London
- Plant used: Haven Seaseven jack up barge
- What we did: Designed and built a custom pile gate. The barge was reviewed to support a 180t crawler crane for piling operations and was then further reviewed with an additional RH28 drill rig on board.
The Challenge
During the contract the piling method had to be changed, which meant that Red7Marine had to mobilise a bored piling rig through the bridges on one of their flat top barges then had to transfer the rig from the floating transportation barge to the jack up barge. Red7Marine provided a full calculation package for this transfer operation and via their operations team successfully carried out the transfer of the rig onto the jack up barge.
The Solution
Red7Marine provided a full calculation package for this transfer operation and via their operations team successfully carried out the transfer of the rig onto the jack up barge.
Custom engineering
A pile gate was designed and built in-house by Red7Marine to accommodate the pile and its preinstalled guides. The gate needed to ensure that the pile was installed in the correct orientation.
Technical support
When the drilling technique was revised, Red7Marine calculated for an alteration to the drilling technique and additional plant required.
Complete package delivery
From planning to completion Red7Marine was able to support the client with all technical aspects of the project, including mobilising the plant and negotiating the many bridges on the way to the site.
Red7Marine provided a full calculation package for this transfer operation and via their operations team successfully carried out the transfer of the rig onto the jack up barge.
Westminster Pier Extension
SEE RELATED CASE STUDIES
Brighton Marina
Phase 2
In order to accommodate a new luxury apartment block in Brighton, part of the marina needed to be reclaimed using sheet piled cofferdams. This would enable the water to be kept out and foundations to be built for the stunning seafront properties. Red7Marine supported the installation of a sheet pile twin wall cofferdam.
Oldbury
Red7Marine installed replacement Active Effluent Discharge Lines at Oldbury power station as part of the on-going care and maintenance works. Red7Marine’s previous project experience on similar projects consisting of works on subsea pipeline and outfalls at Bradwell and Sizewell nuclear power stations, positioned the company as the ideal marine partner for client, Magnox.
Emirates Cable Car
The Emirates cable car was installed to provide a pedestrian link across the River Thames between the Royal Docks and the Greenwich peninsula. Red7Marine worked with Bachy Soletanche in a joint venture to install the foundations for the one-kilometre long cable car using marine rotary bored piling.
Battersea River Pier
Red7Marine secured a contract at Battersea in December 2016 to install new tubular driven steel mooring piles for the Battersea Power Station river bus pontoon installation which is planned to be operational in Autumn 2017. Transport for London (TFL) decided to extend the river bus service after the number of housing developments at Battersea began to increase.
Middleton Sands Navigation Marker
This fast turn-around marine construction project involved the installation of a new tubular steel navigation marker pile at Middleton Sands, Barrow-in-Furness in 2017. The navigation marker was required to identify the sub surface obstructions and enable other vessels in the area to operate safely.
Liverpool 2 Deep Water Port Extension
Red7Marine was the marine partner of choice for BAM Nuttall when they constructed a piled combi-wall as part of the Liverpool 2 Dock Expansion that began in 2014. The construction of the container terminal was supported by four of Red7Marine’s jack up barges; the Haven Seariser 1, Haven Seariser 2 and the Haven Seariser 3 and the Haven Seajack as it carried out rock socket piling works.
Weston-Super-Mare
The Red7Marine team was chosen to provide specialist marine plant and personnel to aid the redevelopment of the Weston-super-Mare Grand Pier after it was destroyed in a fire in 2008. Red7Marine supplied the Haven Seajack 4 assisted in the pier construction works. Its previous experience in pier and marina construction works made it the ideal project partner for this development.
Bradwell Power Station Barrier Wall Removal
Red7Marine is a leading provider of equipment for marine demolition and is skilled in dismantling structures that are beyond the reach of ordinary demolition contractors. In 2012, Red7Marine removed approximately 800 tonnes of steel in the Blackwater Estuary from the Bradwell nuclear power station water intake structure.
Fingringhoe Firing Ranges
Red7Marine installed scour protection and provided remediation on damaged sections of the flood defences to preserve areas of the salt marsh at the Fingringhoe firing ranges in Essex. Scour protection and remediation techniques are used to control erosion in both estuarine and the offshore environments.