Case Study Overview
A modular steel dam system was designed and fabricated in three pieces, 5.6m wide x 6m high total size. A modular approach was taken due to restrictions on available crane size and transport restrictions to site. Support angles were fabricated to match site survey measurements, these were taken to site and fitted by divers.
The three sections were fabricated in steel and fitted with neoprene seals. The lower section weighing 5 ton was lowered into place, the upper section weighing 3 ton was then lowered and bolted to the lower section. The top splash over section was modified and welded on site to suit top detail of the culvert due to overhang detail.
The dam seals were designed to work under gravity for the vertical sealing and when the water was pumped out, the horizontal seals were designed to be compressed by water pressure.
At a glance
- Project: Fabrication of modular dam to allow repair works to intake structure at Abberton reservoir.
- Location: Ipswich R7M fabrication facility
- Programme Duration: 3 week fabrication programme completed on time
- House resources Work: Modular dam system designed by R7M personnel. All fabrication and welding works by R7M personnel.
- Sub-contractors Work: Calculations package by structural engineers
The Solution
This would reduce installation costs by minimising dive time and crane time. By using vertical and horizontal seals in the design, the dam would only require simple installation methods to minimise water ingress.
SEE RELATED CASE STUDIES
Brighton Marina
Phase 2
In order to accommodate a new luxury apartment block in Brighton, part of the marina needed to be reclaimed using sheet piled cofferdams. This would enable the water to be kept out and foundations to be built for the stunning seafront properties. Red7Marine supported the installation of a sheet pile twin wall cofferdam.
Oldbury
Red7Marine installed replacement Active Effluent Discharge Lines at Oldbury power station as part of the on-going care and maintenance works. Red7Marine’s previous project experience on similar projects consisting of works on subsea pipeline and outfalls at Bradwell and Sizewell nuclear power stations, positioned the company as the ideal marine partner for client, Magnox.
Emirates Cable Car
The Emirates cable car was installed to provide a pedestrian link across the River Thames between the Royal Docks and the Greenwich peninsula. Red7Marine worked with Bachy Soletanche in a joint venture to install the foundations for the one-kilometre long cable car using marine rotary bored piling.
Battersea River Pier
Red7Marine secured a contract at Battersea in December 2016 to install new tubular driven steel mooring piles for the Battersea Power Station river bus pontoon installation which is planned to be operational in Autumn 2017. Transport for London (TFL) decided to extend the river bus service after the number of housing developments at Battersea began to increase.
Middleton Sands Navigation Marker
This fast turn-around marine construction project involved the installation of a new tubular steel navigation marker pile at Middleton Sands, Barrow-in-Furness in 2017. The navigation marker was required to identify the sub surface obstructions and enable other vessels in the area to operate safely.
Liverpool 2 Deep Water Port Extension
Red7Marine was the marine partner of choice for BAM Nuttall when they constructed a piled combi-wall as part of the Liverpool 2 Dock Expansion that began in 2014. The construction of the container terminal was supported by four of Red7Marine’s jack up barges; the Haven Seariser 1, Haven Seariser 2 and the Haven Seariser 3 and the Haven Seajack as it carried out rock socket piling works.
Weston-Super-Mare
The Red7Marine team was chosen to provide specialist marine plant and personnel to aid the redevelopment of the Weston-super-Mare Grand Pier after it was destroyed in a fire in 2008. Red7Marine supplied the Haven Seajack 4 assisted in the pier construction works. Its previous experience in pier and marina construction works made it the ideal project partner for this development.
Bradwell Power Station Barrier Wall Removal
Red7Marine is a leading provider of equipment for marine demolition and is skilled in dismantling structures that are beyond the reach of ordinary demolition contractors. In 2012, Red7Marine removed approximately 800 tonnes of steel in the Blackwater Estuary from the Bradwell nuclear power station water intake structure.
Fingringhoe Firing Ranges
Red7Marine installed scour protection and provided remediation on damaged sections of the flood defences to preserve areas of the salt marsh at the Fingringhoe firing ranges in Essex. Scour protection and remediation techniques are used to control erosion in both estuarine and the offshore environments.