Barrier Gardens Pier Extension

Case Study Overview

Red7Marine was contracted by the Port of London Authority to support the Barrier Gardens Pier extension to include higher berthing capacity, whilst also making it safer and greener.

As a part of this contract Red7Marine carried out pile clearance works to ensure the area was safe for piling activity prior to the extension.

At a glance

  • Location: Barrier Gardens Pier
  • Plant used: 250T Haven Seariser 4
  • What we did: Red7Marine cleared the riverbed of natural and man-made obstructions prior to completing the main piling works for the Barrier Gardens Pier extension

The Challenge

The purpose of the pile clearance was to remove any natural or man-made obstructions from the riverbed over two locations where the berthing piles for the new pontoon at Barrier Gardens were being installed.

The team expected to find wires, mooring ropes and timber. Both natural and manmade features were found during the clearance including wires and timber as expected. Fortunately, no obstructions that would have caused issues for the main works were found. However, on previous occasions, Red7Marine’s findings have been larger, including a 20t concrete block, old timber piles and a Victorian anchor.

Barrier Gardens Challenge

The Solution

The task was completed using a 30t long reach excavator from WM Plant Hire working on the 250T Haven Seariser 4. The barge was put into position using survey assistance to ensure the legs did not sit within 5m of any anomalies.
Both pile positions were cleared ahead of the main piling works to minimise the risk of delays to the project before the piling barge arrived on site for the main works.

A UXO desktop study and geophysical survey completed in April 2020 highlighted a selection of potential anomalies within the site boundary.

Whilst these anomalies were a set distance from both planned pile locations and jack-up leg positions, there was a risk of potential UXO’s within the area. Red7Marine utilised a UXO to oversee the pile clearance works in the unlikely event that a UXO was encountered. A UXO brief was also and a site specific UXO emergency response plan produced.

For the main works, Red7Marine carried out the installation of two 38m length piles into the riverbed using both a vibratory and impact hammer, to support the extension which is due to be fully operational later this Summer. The extension will enable larger vessels, such as PLA flagship, London Titan, to dock directly at the pier, making it quicker and safer for crews to get on and off at the start and end of their shifts.

Red7Marine mobilised the Haven Seaseven 400t jack-up barge for the works and the Haven Seaforth flat top barge was also used for plant and equipment. The contract was completed within one week of mobilisation.

Barrier Gardens Solution

Complete Package Delivery

Red7Marine provided equipment, crew and engineering support to the project to ensure our clients’ successful delivery.

Solutions Provider

Red7Marine provided specialist barge and marine experience to the project.

Skilled Team

Red7Marine’s operations and engineering teams are all highly skilled and experienced in the marine environment providing partners with an industry-leading service.

THE MARINE PARTNER OF CHOICE

SEE RELATED CASE STUDIES

Westminster

Westminster Pier Extension

The Westminster Pier Extension allows more frequent River Bus services between Woolwich and North Greenwich to Westminster. The extension is a key part of the River Action Plan to improve TfL’s piers and increase capacity for passengers before 2020. Red7Marine designed and built a custom pile gate for the project. The barge was reviewed to support a 180t crawler crane for piling operations and was then further reviewed with an additional RH28 drill rig on board.

Read more →

Brighton

Brighton Marina
Phase 2

In order to accommodate a new luxury apartment block in Brighton, part of the marina needed to be reclaimed using sheet piled cofferdams. This would enable the water to be kept out and foundations to be built for the stunning seafront properties. Red7Marine supported the installation of a sheet pile twin wall cofferdam.

Read more →

Oldbury

Oldbury

Red7Marine installed replacement Active Effluent Discharge Lines at Oldbury power station as part of the on-going care and maintenance works. Red7Marine’s previous project experience on similar projects consisting of works on subsea pipeline and outfalls at Bradwell and Sizewell nuclear power stations, positioned the company as the ideal marine partner for client, Magnox.

Read more →

Emirates

Emirates Cable Car

The Emirates cable car was installed to provide a pedestrian link across the River Thames between the Royal Docks and the Greenwich peninsula. Red7Marine worked with Bachy Soletanche in a joint venture to install the foundations for the one-kilometre long cable car using marine rotary bored piling.

Read more →

Middleton

Middleton Sands Navigation Marker

This fast turn-around marine construction project involved the installation of a new tubular steel navigation marker pile at Middleton Sands, Barrow-in-Furness in 2017. The navigation marker was required to identify the sub surface obstructions and enable other vessels in the area to operate safely.

Read more →

Liverpool 2

Liverpool 2 Deep Water Port Extension

Red7Marine was the marine partner of choice for BAM Nuttall when they constructed a piled combi-wall as part of the Liverpool 2 Dock Expansion that began in 2014. The construction of the container terminal was supported by four of Red7Marine’s jack up barges; the Haven Seariser 1, Haven Seariser 2 and the Haven Seariser 3 and the Haven Seajack as it carried out rock socket piling works.

Read more →

Weston Super Mare

Weston-Super-Mare

The Red7Marine team was chosen to provide specialist marine plant and personnel to aid the redevelopment of the Weston-super-Mare Grand Pier after it was destroyed in a fire in 2008. Red7Marine supplied the Haven Seajack 4 assisted in the pier construction works. Its previous experience in pier and marina construction works made it the ideal project partner for this development.

Read more →

Bradwell

Bradwell Power Station Barrier Wall Removal

Red7Marine is a leading provider of equipment for marine demolition and is skilled in dismantling structures that are beyond the reach of ordinary demolition contractors. In 2012, Red7Marine removed approximately 800 tonnes of steel in the Blackwater Estuary from the Bradwell nuclear power station water intake structure.

Read more →

Fingringhoe

Fingringhoe Firing Ranges

Red7Marine installed scour protection and provided remediation on damaged sections of the flood defences to preserve areas of the salt marsh at the Fingringhoe firing ranges in Essex. Scour protection and remediation techniques are used to control erosion in both estuarine and the offshore environments.

Read more →

Get in touch with our expert team

or speak to our team: 01255 886710

British Standards ISO British Standards ISO British Standards ISO Achilles Building Confidence IEMA Construction Line Chas Ijuboa CPA National Workboat Association ICE Mates in Mind AF Covenenant Gold award

“Our relationship with Red7Marine and their Personnel through all stages of this challenging Project has been based on partnership and co-operation. A huge consideration was given at the initial phase to identify potential difficulties. This has been followed by development of various scenarios and methods of addressing such difficulties which provided a great benefit during actual works. We look forward to continuing the relationship with the Red7Marine team.”

Kate Sellers, Site Agent BAM Nuttall